Project History

Project Milestones

The project schedule, milestones, key activities, and civic engagement are listed below. The service began operating in early 2020, and construction on all project elements is now complete.

 MilestoneActivities
Fall 2016 – Spring 2017Conceptual EngineeringLocate stations, identify desired passenger amenities, propose street design concepts, develop project branding
October 2016Stakeholder Meeting
December 2016Public Meeting
February 2017Stakeholder Meeting
May 2017Public Meeting
Summer 2017Preliminary Engineering BeginsAdvance the design of stations, street cross-sections, amenities and a terminal in the RI Hospital area. Work with local stakeholder to further develop the design concepts.
June 2017Open House for Businesses/Property Owners
Fall 2017Final EngineeringComplete engineering for all design elements and create construction specifications.
October 2017Stakeholder Meeting
February 2018Stakeholder Meeting
March 2018Public Meeting
Winter 2018Property Owner/Business Outreach
Mid 2018Construction BeginsConstruct stations and street improvements. Note: the Providence Station Transit Center will be constructed as part of a separate RIDOT project.
September 2018Stakeholder Meeting
2018-2020Construction
2021DTC Ribbon-Cutting Event – June 21, 2021Driver comfort station to be completed