The project schedule, milestones, key activities, and civic engagement are listed below. The service began operating in early 2020, and construction on all project elements is now complete.
Milestone | Activities | |
---|---|---|
Fall 2016 – Spring 2017 | Conceptual Engineering | Locate stations, identify desired passenger amenities, propose street design concepts, develop project branding |
October 2016 | Stakeholder Meeting | |
December 2016 | Public Meeting | |
February 2017 | Stakeholder Meeting | |
May 2017 | Public Meeting | |
Summer 2017 | Preliminary Engineering Begins | Advance the design of stations, street cross-sections, amenities and a terminal in the RI Hospital area. Work with local stakeholder to further develop the design concepts. |
June 2017 | Open House for Businesses/Property Owners | |
Fall 2017 | Final Engineering | Complete engineering for all design elements and create construction specifications. |
October 2017 | Stakeholder Meeting | |
February 2018 | Stakeholder Meeting | |
March 2018 | Public Meeting | |
Winter 2018 | Property Owner/Business Outreach | |
Mid 2018 | Construction Begins | Construct stations and street improvements. Note: the Providence Station Transit Center will be constructed as part of a separate RIDOT project. |
September 2018 | Stakeholder Meeting | |
2018-2020 | Construction | |
2021 | DTC Ribbon-Cutting Event – June 21, 2021 | Driver comfort station to be completed |